How we helped
Richard Crookes Constructions
Project Name: The Braidwood/Harden Hospitals
Works: FRP supply and install over 6000m2 of works
Challenges: Subcontractor on form work to deck Braidwood Hospital labour power insufficient – to resolve the issue, Superstruct sourced extra labour to assist contractor and got the formwork time line back on track and with in program time lines for client.
Project achievements:
- Fastest Polyvoid suspended slab install in Australia
- Design change program saving 2 weeks + reducing 40 tonne REO
- Design changed to assist with safety on site risk reduced by 50%.